What this skill does
# Manufacturing Process Planning Skill
## Purpose
The Manufacturing Process Planning skill provides capabilities for developing comprehensive manufacturing process plans including operation sequencing, work instructions, and quality controls for mechanical component production.
## Capabilities
- Operation sequence development
- Machine and tooling selection
- Cycle time estimation
- Inspection point specification
- Work instruction creation
- Process FMEA development
- Control plan generation
- Cost estimation and optimization
## Usage Guidelines
### Process Planning Framework
#### Information Gathering
1. **Design Requirements**
- Part drawing and model
- Material specification
- Tolerance requirements
- Surface finish requirements
- Special requirements (certifications, traceability)
2. **Production Requirements**
- Annual volume
- Lot sizes
- Lead time requirements
- Budget constraints
3. **Available Resources**
- Machine capabilities
- Tooling inventory
- Skilled labor
- Quality equipment
### Operation Sequencing
#### Sequence Development Principles
```
General sequence:
1. Raw material preparation
2. Primary forming/roughing
3. Secondary operations
4. Finishing operations
5. Heat treatment (if required)
6. Final machining (post-heat treat)
7. Surface treatment/coating
8. Final inspection
9. Packaging
```
#### Operation Selection Matrix
| Feature | Possible Operations | Selection Criteria |
|---------|--------------------|--------------------|
| External cylinder | Turning, grinding | Tolerance, finish |
| Internal cylinder | Boring, drilling, reaming | Diameter, depth |
| Flat surface | Milling, grinding, lapping | Flatness, finish |
| Gear teeth | Hobbing, shaping, grinding | Accuracy, volume |
| Thread | Tapping, thread milling, rolling | Size, accuracy |
| Heat treat | Quench/temper, carburize, nitride | Hardness, depth |
### Machine Selection
#### Capability Assessment
```
Selection criteria:
- Workpiece size vs machine envelope
- Required tolerances vs machine capability
- Surface finish capability
- Spindle power vs material removal
- Tool capacity
- Automation potential
```
#### Process Capability
```
Typical capabilities:
Turning: IT7-IT9, Ra 0.8-3.2 um
Milling: IT7-IT10, Ra 0.8-6.3 um
Grinding: IT5-IT7, Ra 0.1-0.8 um
EDM: IT6-IT8, Ra 0.2-6.3 um
Honing: IT4-IT6, Ra 0.05-0.4 um
```
### Cycle Time Estimation
#### Time Components
```
Total cycle time = Setup time + Processing time + Non-productive time
Processing time per operation:
T_process = (L + A) / (f * N) + tool change time
Where:
L = length of cut
A = approach distance
f = feed rate
N = spindle speed
```
#### Standard Times
| Activity | Typical Time |
|----------|--------------|
| Load/unload (manual) | 15-60 seconds |
| Tool change (CNC) | 3-10 seconds |
| Index (turret) | 1-3 seconds |
| Probe cycle | 5-15 seconds |
| Deburr (manual) | 30-120 seconds |
### Work Instructions
#### Content Requirements
1. **Header Information**
- Part number and revision
- Operation number and description
- Work center/machine
- Standard time
2. **Setup Instructions**
- Fixture identification
- Tool list
- Work offset procedures
- Program number
3. **Operating Instructions**
- Step-by-step procedures
- Critical parameters
- Safety requirements
- Quality checks
4. **Visual Aids**
- Photos of setup
- Diagrams of critical dimensions
- Defect examples (visual standards)
### Process FMEA
#### FMEA Structure
```
Process Step -> Potential Failure Mode -> Effect -> Cause
Severity (S): 1-10 scale
Occurrence (O): 1-10 scale
Detection (D): 1-10 scale
RPN = S x O x D
Actions required for RPN > 100 (typically)
```
#### Common Process Failure Modes
| Process | Failure Mode | Cause | Detection |
|---------|--------------|-------|-----------|
| Machining | Dimension out of tolerance | Tool wear | In-process gage |
| Heat treat | Incorrect hardness | Temperature error | Hardness test |
| Welding | Porosity | Contamination | NDT |
| Assembly | Missing component | Operator error | Check sheet |
### Control Plan
#### Control Plan Elements
```
For each operation:
- Process step
- Machine/device
- Characteristic (dimension, property)
- Specification/tolerance
- Measurement method
- Sample size and frequency
- Control method
- Reaction plan
```
## Process Integration
- ME-017: Manufacturing Process Planning
## Input Schema
```json
{
"part_info": {
"part_number": "string",
"revision": "string",
"material": "string"
},
"design_requirements": {
"drawing_reference": "string",
"critical_dimensions": "array",
"surface_finish_requirements": "array"
},
"production_requirements": {
"annual_volume": "number",
"lot_size": "number",
"lead_time": "number (weeks)"
},
"available_equipment": "array of machine types"
}
```
## Output Schema
```json
{
"process_plan": {
"routing_number": "string",
"operations": [
{
"op_number": "number",
"description": "string",
"work_center": "string",
"setup_time": "number (min)",
"cycle_time": "number (min)",
"tooling": "array",
"inspection_points": "array"
}
],
"total_lead_time": "number (days)"
},
"work_instructions": "array of document references",
"process_fmea": "document reference",
"control_plan": "document reference",
"cost_estimate": {
"material": "number",
"labor": "number",
"overhead": "number",
"total": "number"
}
}
```
## Best Practices
1. Consider all design requirements before sequencing
2. Minimize setups and part handling
3. Group operations by work center when possible
4. Include quality gates at critical operations
5. Document all assumptions and alternatives
6. Review with production team before release
## Integration Points
- Connects with GD&T Drawing for requirements
- Feeds into CNC Programming for machining ops
- Supports FAI Inspection for verification
- Integrates with Quality for control plans
Related in General
modeling-omnistudio-epc-catalog
IncludedSalesforce Industries CME EPC product-modeling skill for Product2-based catalog creation. Use when creating EPC products, configuring product attributes, building offer bundles with Product Child Items, or reviewing EPC DataPack JSON metadata for product catalog changes. TRIGGER when: user creates or updates Product2 EPC records, AttributeAssignment payloads, AttributeMetadata/AttributeDefaultValues, Offer bundles, or ProductChildItem relationships. DO NOT TRIGGER when: designing OmniScripts/FlexCards/Integration Procedures (use building-omnistudio-omniscript, building-omnistudio-flexcard, or building-omnistudio-integration-procedure), implementing Apex business logic (use generating-apex), or troubleshooting deployment pipelines (use deploying-metadata).
relationship-science-coach
IncludedUse this skill for direct, practical adult relationship coaching: couples conflict, repair, trust, marriage, dating, flirting, attachment patterns, emotional connection, sex, desire differences, eroticism, kink negotiation, affection, love languages, breakups, and long-term passion. Draw on Gottman, EFT and Hold Me Tight, attachment science, modern sex research, Perel, Nagoski, Kerner, Schnarch, Love and Stosny, and flexible love-language tools. Be concrete and low-hedge. Redirect only for imminent danger, abuse, coercive control, minors, non-consent, self-harm, stalking, or medical/legal/psychiatric decisions.
building-sf-integrations
IncludedSalesforce integration architecture and runtime plumbing with 120-point scoring. Use this skill to set up Named Credentials, External Credentials, External Services, REST/SOAP callout patterns, Platform Events, and Change Data Capture. TRIGGER when: user sets up Named Credentials, External Services, REST/SOAP callouts, Platform Events, CDC, or touches .namedCredential-meta.xml files. DO NOT TRIGGER when: Connected App/OAuth config (use configuring-connected-apps), Apex-only logic (use generating-apex), or data import/export (use handling-sf-data).
venue-templates
IncludedAccess comprehensive LaTeX templates, formatting requirements, and submission guidelines for major scientific publication venues (Nature, Science, PLOS, IEEE, ACM), academic conferences (NeurIPS, ICML, CVPR, CHI), research posters, and grant proposals (NSF, NIH, DOE, DARPA). This skill should be used when preparing manuscripts for journal submission, conference papers, research posters, or grant proposals and need venue-specific formatting requirements and templates.
let-fate-decide
IncludedDraws the 12 Houses of the Zodiac Tarot spread to inject entropy into planning when prompts are vague, ambiguous, or casually delegated. Interprets the spread to guide next steps. Use when the user says 'let fate decide', 'YOLO', 'whatever', 'idk', or other nonchalant phrases, makes Yu-Gi-Oh references, or when you are about to arbitrarily pick between multiple reasonable approaches. Prefer over ask-questions-if-underspecified when the user's tone is casual or playful rather than precision-seeking.
net-ops
IncludedCross-platform network troubleshooting (Windows, macOS, Linux) via local or remote shell. Use for: DNS broken, can't resolve hostnames, nslookup/dig works but apps fail, NRPT, WFP, scutil, /etc/resolver, systemd-resolved, /etc/resolv.conf, NetworkManager, VPN DNS leak residue (ProtonVPN/Mullvad/WireGuard/AnyConnect), AV/firewall blocking DNS or DoH, Tailscale DNS interaction, intermittent connectivity, remote diagnostics over SSH.